27 Project Planning & Scheduling questions from the Site & Project Mgmt bank, written for Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd.
Free to start: the 2-minute CE readiness check — six questions and a result.
A.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
B.shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
C.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
D.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
Answer + AI explanation with Pro
2. Which term means: "deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates"?
Junior
A.CPM vs PERT
B.Resource levelling vs smoothing
C.Crashing
D.Primavera P6
Answer + AI explanation with Pro
3. Which statement is correct?
Junior
A.CPM vs PERT — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
B.CPM vs PERT — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
C.CPM vs PERT — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
D.CPM vs PERT — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
Answer + AI explanation with Pro
4. What is Critical path?
Junior
A.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
B.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
C.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
D.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
Answer + AI explanation with Pro
5. Which term means: "longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion"?
Junior
A.Resource levelling vs smoothing
B.Look-ahead schedule
C.S-curve
D.Critical path
Answer + AI explanation with Pro
6. Which statement is correct?
Junior
A.Critical path — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
B.Critical path — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
C.Critical path — enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
D.Critical path — longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
Answer + AI explanation with Pro
7. What is Total float vs free float?
Junior
A.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
B.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
C.shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
D.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
Answer + AI explanation with Pro
8. Which term means: "time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former"?
Junior
A.Total float vs free float
B.CPM vs PERT
C.Primavera P6
D.Crashing
Answer + AI explanation with Pro
9. Which statement is correct?
Junior
A.Total float vs free float — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
B.Total float vs free float — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
C.Total float vs free float — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
D.Total float vs free float — shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
Answer + AI explanation with Pro
10. What is Primavera P6?
Mid
A.enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
B.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
C.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
D.shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
Answer + AI explanation with Pro
11. Which term means: "enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date"?
Mid
A.Crashing
B.Look-ahead schedule
C.Earned value metrics
D.Primavera P6
Answer + AI explanation with Pro
12. Which statement is correct?
Mid
A.Primavera P6 — longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
B.Primavera P6 — shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
C.Primavera P6 — enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
D.Primavera P6 — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Answer + AI explanation with Pro
13. What is S-curve?
Junior
A.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
B.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
C.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Answer + AI explanation with Pro
14. Which term means: "plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow"?
Junior
A.Primavera P6
B.S-curve
C.Resource levelling vs smoothing
D.CPM vs PERT
Answer + AI explanation with Pro
15. Which statement is correct?
Junior
A.S-curve — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
B.S-curve — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
C.S-curve — shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
D.S-curve — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
Answer + AI explanation with Pro
16. What is Earned value metrics?
Mid
A.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
B.shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
C.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Answer + AI explanation with Pro
17. Which term means: "CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI"?
Mid
A.Earned value metrics
B.Primavera P6
C.Total float vs free float
D.Resource levelling vs smoothing
Answer + AI explanation with Pro
18. Which statement is correct?
Mid
A.Earned value metrics — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
B.Earned value metrics — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
C.Earned value metrics — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
D.Earned value metrics — longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
Answer + AI explanation with Pro
19. What is Look-ahead schedule?
Mid
A.rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
B.CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
C.enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Answer + AI explanation with Pro
20. Which term means: "rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete"?
Mid
A.Resource levelling vs smoothing
B.Crashing
C.Total float vs free float
D.Look-ahead schedule
Answer + AI explanation with Pro
21. Which statement is correct?
Mid
A.Look-ahead schedule — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
B.Look-ahead schedule — shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
C.Look-ahead schedule — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
D.Look-ahead schedule — enterprise scheduler with WBS, activity codes, resource and cost loading, baselines and FS, SS, FF, SF relationships with lag, updated against a data date
Answer + AI explanation with Pro
22. What is Resource levelling vs smoothing?
Senior
A.longest chain of dependent activities through the network, carrying zero total float and fixing the project duration, so any delay on it delays completion
B.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
C.shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
D.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
Answer + AI explanation with Pro
23. Which term means: "shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks"?
Senior
A.Total float vs free float
B.Resource levelling vs smoothing
C.Primavera P6
D.S-curve
Answer + AI explanation with Pro
24. Which statement is correct?
Senior
A.Resource levelling vs smoothing — plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
B.Resource levelling vs smoothing — CPI = EV/AC and SPI = EV/PV, values below 1 meaning over budget or behind schedule, with estimate at completion taken as BAC/CPI
C.Resource levelling vs smoothing — shifting activities to keep demand within a resource limit even if the finish moves, versus rescheduling only within available float to flatten peaks
D.Resource levelling vs smoothing — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
Answer + AI explanation with Pro
25. What is Crashing?
Senior
A.plot of cumulative planned versus actual progress or cost against time, slow at both ends and steep in the middle, used for monitoring and cash flow
B.deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
C.time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
D.shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
Answer + AI explanation with Pro
26. Which term means: "shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change"?
Senior
A.Crashing
B.S-curve
C.Earned value metrics
D.Look-ahead schedule
Answer + AI explanation with Pro
27. Which statement is correct?
Senior
A.Crashing — shortening the schedule by adding resources to critical activities with the lowest cost slope first, rechecking after each step because the path may change
B.Crashing — deterministic single-duration activity network versus a probabilistic event network using expected time (a + 4m + b)/6 from optimistic, likely and pessimistic estimates
C.Crashing — time an activity can slip without delaying the project versus without delaying its immediate successor, the latter never exceeding the former
D.Crashing — rolling 2 to 6 week plan drawn from the master schedule after clearing drawing, material, permit and labour constraints, tracked by percent plan complete
Answer + AI explanation with Pro