27 Project Execution questions from the Production & Plant bank, written for Indian campus drives and tech interviews. Every question has a verified answer and an AI-tutor explanation on placd.
Free to start: the 2-minute ME readiness check — six questions and a result.
A.functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
B.schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun
C.single contractor delivering engineering, procurement and construction of a plant, usually lump-sum turnkey against a fixed date
D.categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
Answer + AI explanation with Pro
2. Which term means: "single contractor delivering engineering, procurement and construction of a plant, usually lump-sum turnkey against a fixed date"?
Junior
A.EPC contract
B.Critical path
C.Earned value indices
D.Site acceptance test
Answer + AI explanation with Pro
3. Which statement is correct?
Junior
A.EPC contract — longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
B.EPC contract — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
C.EPC contract — single contractor delivering engineering, procurement and construction of a plant, usually lump-sum turnkey against a fixed date
D.EPC contract — categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
Answer + AI explanation with Pro
4. What is Work breakdown structure?
Junior
A.mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
B.longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
C.hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
D.contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
Answer + AI explanation with Pro
5. Which term means: "hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out"?
Junior
A.Factory acceptance test
B.Work breakdown structure
C.EPC contract
D.Performance guarantee test
Answer + AI explanation with Pro
6. Which statement is correct?
Junior
A.Work breakdown structure — contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
B.Work breakdown structure — hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
C.Work breakdown structure — re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces
D.Work breakdown structure — longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
Answer + AI explanation with Pro
7. What is Factory acceptance test?
Junior
A.functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
B.contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
C.single contractor delivering engineering, procurement and construction of a plant, usually lump-sum turnkey against a fixed date
D.mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
Answer + AI explanation with Pro
8. Which term means: "functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client"?
Junior
A.Performance guarantee test
B.Earned value indices
C.Factory acceptance test
D.Work breakdown structure
Answer + AI explanation with Pro
9. Which statement is correct?
Junior
A.Factory acceptance test — hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
B.Factory acceptance test — contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
C.Factory acceptance test — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
D.Factory acceptance test — schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun
Answer + AI explanation with Pro
10. What is Critical path?
Mid
A.hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
B.functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
C.re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces
D.longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
Answer + AI explanation with Pro
11. Which term means: "longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration"?
Mid
A.Factory acceptance test
B.EPC contract
C.Critical path
D.Work breakdown structure
Answer + AI explanation with Pro
12. Which statement is correct?
Mid
A.Critical path — contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
B.Critical path — longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
C.Critical path — categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
D.Critical path — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
Answer + AI explanation with Pro
13. What is Earned value indices?
Mid
A.hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
B.mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
C.schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun
D.categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
Answer + AI explanation with Pro
14. Which term means: "schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun"?
Mid
A.Factory acceptance test
B.Critical path
C.Earned value indices
D.Punch list
Answer + AI explanation with Pro
15. Which statement is correct?
Mid
A.Earned value indices — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
B.Earned value indices — mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
C.Earned value indices — categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
D.Earned value indices — schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun
Answer + AI explanation with Pro
16. What is Site acceptance test?
Mid
A.single contractor delivering engineering, procurement and construction of a plant, usually lump-sum turnkey against a fixed date
B.contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
C.hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
D.re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces
Answer + AI explanation with Pro
17. Which term means: "re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces"?
Mid
A.Performance guarantee test
B.Punch list
C.EPC contract
D.Site acceptance test
Answer + AI explanation with Pro
18. Which statement is correct?
Mid
A.Site acceptance test — categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
B.Site acceptance test — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
C.Site acceptance test — schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun
D.Site acceptance test — re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces
Answer + AI explanation with Pro
19. What is Commissioning sequence?
Mid
A.hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
B.mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
C.longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
D.contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
Answer + AI explanation with Pro
20. Which term means: "mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test"?
Mid
A.Commissioning sequence
B.Performance guarantee test
C.EPC contract
D.Punch list
Answer + AI explanation with Pro
21. Which statement is correct?
Mid
A.Commissioning sequence — categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
B.Commissioning sequence — mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
C.Commissioning sequence — longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
D.Commissioning sequence — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
Answer + AI explanation with Pro
22. What is Performance guarantee test?
Senior
A.longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
B.single contractor delivering engineering, procurement and construction of a plant, usually lump-sum turnkey against a fixed date
C.functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
D.contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
Answer + AI explanation with Pro
23. Which term means: "contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall"?
Senior
A.Work breakdown structure
B.EPC contract
C.Site acceptance test
D.Performance guarantee test
Answer + AI explanation with Pro
24. Which statement is correct?
Senior
A.Performance guarantee test — functional and performance test of equipment at the vendor's works before dispatch, witnessed by the client
B.Performance guarantee test — contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
C.Performance guarantee test — mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
D.Performance guarantee test — schedule performance index EV/PV and cost performance index EV/AC, with values below 1 signalling slippage or overrun
Answer + AI explanation with Pro
25. What is Punch list?
Senior
A.re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces
B.mechanical completion, pre-commissioning (flushing, loop checks), no-load and load trials, then the performance guarantee test
C.categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
D.longest chain of dependent activities with zero float, found from forward and backward passes, which fixes the project duration
Answer + AI explanation with Pro
26. Which term means: "categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period"?
Senior
A.EPC contract
B.Punch list
C.Critical path
D.Commissioning sequence
Answer + AI explanation with Pro
27. Which statement is correct?
Senior
A.Punch list — contractual demonstration of guaranteed capacity, efficiency and power consumption, with liquidated damages payable for any shortfall
B.Punch list — hierarchical decomposition of the whole scope into work packages, following the 100% rule that nothing is left out
C.Punch list — re-test of equipment after installation at site to prove it works with the real utilities, controls and interfaces
D.Punch list — categorised list of outstanding items at handover, with A items to be cleared before start-up and B items allowed during the defect liability period
Answer + AI explanation with Pro