1. What is ETAP?

Junior
  1. A.integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies
  2. B.IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  3. C.load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC
  4. D.log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves

Answer + AI explanation with Pro

2. Which term means: "integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies"?

Junior
  1. A.PSS/E
  2. B.ETAP
  3. C.Motor starting study
  4. D.IEC 60909 method

Answer + AI explanation with Pro

3. Which statement is correct?

Junior
  1. A.ETAP — simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  2. B.ETAP — IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  3. C.ETAP — RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters
  4. D.ETAP — integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies

Answer + AI explanation with Pro

4. What is DIgSILENT PowerFactory?

Junior
  1. A.MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  2. B.utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  3. C.electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps
  4. D.simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out

Answer + AI explanation with Pro

5. Which term means: "utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies"?

Junior
  1. A.IEC 60909 method
  2. B.Simscape Electrical
  3. C.Motor starting study
  4. D.DIgSILENT PowerFactory

Answer + AI explanation with Pro

6. Which statement is correct?

Junior
  1. A.DIgSILENT PowerFactory — short-circuit calculation using an equivalent voltage source at the fault with voltage factor c (1.1 for maximum) to give the initial symmetrical current Ik''
  2. B.DIgSILENT PowerFactory — utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  3. C.DIgSILENT PowerFactory — RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters
  4. D.DIgSILENT PowerFactory — MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing

Answer + AI explanation with Pro

7. What is PSCAD/EMTDC?

Junior
  1. A.MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  2. B.electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps
  3. C.IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  4. D.Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC

Answer + AI explanation with Pro

8. Which term means: "electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps"?

Junior
  1. A.Arc flash study
  2. B.Simscape Electrical
  3. C.ETAP
  4. D.PSCAD/EMTDC

Answer + AI explanation with Pro

9. Which statement is correct?

Junior
  1. A.PSCAD/EMTDC — integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies
  2. B.PSCAD/EMTDC — utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  3. C.PSCAD/EMTDC — electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps
  4. D.PSCAD/EMTDC — Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC

Answer + AI explanation with Pro

10. What is PSS/E?

Junior
  1. A.MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  2. B.utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  3. C.simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  4. D.Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC

Answer + AI explanation with Pro

11. Which term means: "Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC"?

Junior
  1. A.Motor starting study
  2. B.Time-current curve plot
  3. C.Arc flash study
  4. D.PSS/E

Answer + AI explanation with Pro

12. Which statement is correct?

Junior
  1. A.PSS/E — simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  2. B.PSS/E — MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  3. C.PSS/E — Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC
  4. D.PSS/E — load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC

Answer + AI explanation with Pro

13. What is IEC 60909 method?

Mid
  1. A.utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  2. B.load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC
  3. C.electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps
  4. D.short-circuit calculation using an equivalent voltage source at the fault with voltage factor c (1.1 for maximum) to give the initial symmetrical current Ik''

Answer + AI explanation with Pro

14. Which term means: "short-circuit calculation using an equivalent voltage source at the fault with voltage factor c (1.1 for maximum) to give the initial symmetrical current Ik''"?

Mid
  1. A.Arc flash study
  2. B.RMS vs EMT simulation
  3. C.ETAP
  4. D.IEC 60909 method

Answer + AI explanation with Pro

15. Which statement is correct?

Mid
  1. A.IEC 60909 method — utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  2. B.IEC 60909 method — IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  3. C.IEC 60909 method — short-circuit calculation using an equivalent voltage source at the fault with voltage factor c (1.1 for maximum) to give the initial symmetrical current Ik''
  4. D.IEC 60909 method — electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps

Answer + AI explanation with Pro

16. What is Arc flash study?

Mid
  1. A.IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  2. B.simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  3. C.MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  4. D.load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC

Answer + AI explanation with Pro

17. Which term means: "IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance"?

Mid
  1. A.Motor starting study
  2. B.Time-current curve plot
  3. C.RMS vs EMT simulation
  4. D.Arc flash study

Answer + AI explanation with Pro

18. Which statement is correct?

Mid
  1. A.Arc flash study — simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  2. B.Arc flash study — IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  3. C.Arc flash study — RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters
  4. D.Arc flash study — MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing

Answer + AI explanation with Pro

19. What is Time-current curve plot?

Mid
  1. A.Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC
  2. B.log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves
  3. C.integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies
  4. D.electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps

Answer + AI explanation with Pro

20. Which term means: "log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves"?

Mid
  1. A.Time-current curve plot
  2. B.Simscape Electrical
  3. C.IEC 60909 method
  4. D.Arc flash study

Answer + AI explanation with Pro

21. Which statement is correct?

Mid
  1. A.Time-current curve plot — integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies
  2. B.Time-current curve plot — MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  3. C.Time-current curve plot — load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC
  4. D.Time-current curve plot — log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves

Answer + AI explanation with Pro

22. What is Simscape Electrical?

Mid
  1. A.utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  2. B.log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves
  3. C.MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  4. D.Siemens planning tool for large-network load flow and dynamic stability whose model format is used for the Indian grid by CEA and NLDC

Answer + AI explanation with Pro

23. Which term means: "MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing"?

Mid
  1. A.IEC 60909 method
  2. B.Simscape Electrical
  3. C.PSS/E
  4. D.Time-current curve plot

Answer + AI explanation with Pro

24. Which statement is correct?

Mid
  1. A.Simscape Electrical — MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  2. B.Simscape Electrical — simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  3. C.Simscape Electrical — utility-grade tool for load flow, RMS/EMT dynamic simulation, grid-code compliance and contingency analysis used for transmission-level studies
  4. D.Simscape Electrical — integrated power-system analysis suite widely used in India for load flow, short circuit, arc flash, relay coordination, motor starting and harmonic studies

Answer + AI explanation with Pro

25. What is Motor starting study?

Mid
  1. A.simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out
  2. B.log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves
  3. C.load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC
  4. D.IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance

Answer + AI explanation with Pro

26. Which term means: "simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out"?

Mid
  1. A.N-1 contingency analysis
  2. B.Arc flash study
  3. C.Motor starting study
  4. D.ETAP

Answer + AI explanation with Pro

27. Which statement is correct?

Mid
  1. A.Motor starting study — RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters
  2. B.Motor starting study — load flow re-run with each element out of service to confirm no overload or voltage violation, a planning requirement under the IEGC
  3. C.Motor starting study — log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves
  4. D.Motor starting study — simulation confirming bus voltage dip during direct-on-line start stays above about 80% so running motors and contactors do not drop out

Answer + AI explanation with Pro

28. What is RMS vs EMT simulation?

Senior
  1. A.RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters
  2. B.log-log overlay of series protective devices in ETAP Star to verify grading margin, CT saturation and cable damage curves
  3. C.MATLAB/Simulink block library for converters, machines and drives, used for control design and hardware-in-the-loop testing
  4. D.short-circuit calculation using an equivalent voltage source at the fault with voltage factor c (1.1 for maximum) to give the initial symmetrical current Ik''

Answer + AI explanation with Pro

29. Which term means: "RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters"?

Senior
  1. A.Motor starting study
  2. B.RMS vs EMT simulation
  3. C.PSS/E
  4. D.PSCAD/EMTDC

Answer + AI explanation with Pro

30. Which statement is correct?

Senior
  1. A.RMS vs EMT simulation — electromagnetic transient program that simulates switching, lightning, HVDC and FACTS behaviour with microsecond time steps
  2. B.RMS vs EMT simulation — IEEE 1584 calculation of incident energy in cal/cm² and arc-flash boundary from bolted fault current, clearing time and working distance
  3. C.RMS vs EMT simulation — short-circuit calculation using an equivalent voltage source at the fault with voltage factor c (1.1 for maximum) to give the initial symmetrical current Ik''
  4. D.RMS vs EMT simulation — RMS uses phasor models with millisecond steps for electromechanical stability; EMT solves instantaneous waveforms with microsecond steps for converters

Answer + AI explanation with Pro

Showing 30 of 33 Power System Software questions — the full set, with answers, explanations and an AI tutor on every question, is inside.

Free to start

Start with a free readiness check

Sign up free for the 2-minute EE readiness check and a scored result. Answers, explanations and the AI tutor on every Power System Software question come with Pro.

Take the free EE readiness check

or take a mock interview set up for this area

24,000+ questions & coding problemsSoftware & IT16,274 questionsGovernment jobs26 examsAptitudenew questions every timeAI practice interviewwith feedback65 topics to practiseMechanical1,149 questionsGATE ME9 papersEngineering Mathematics381 questions2-minute checkfreeDSA Problems1,422Civil1,005 questionsGATE CE9 papersCS Fundamentals1,209 questionsYour scores6 skillsSystem Design25Electrical / EEE1,047 questionsGATE EE9 papersRun your codeC++ · Java · PythonLow-Level Design144Electronics & Comm.975 questionsGATE EC9 papersAI help on every questionFull-Stack6,282Chemical1,005 questionsGATE CH9 papersAI whiteboardsystem designWork abroadEurope · remote · transfersESE ME1 paperGATE practice papers2019–2026ESE CE1 paperDate alertsbefore the last dateESE EE1 paperBehavioural courseHR round practiceESE ET1 paperResume optimizerProSSC JE ME1 paperApplication trackerSSC JE CE1 paperCompany-wise prepSSC JE EE1 paperRole roadmapsRRB JE1 subjectPriced in ₹UPI · cardsISRO SC1 paperGATE CS9 papersIBPS SO IT1 paperUGC NET CS1 paperSSC CGL26 papersIBPS PO26 papersRRB NTPC26 papersSSC CHSL26 papersIBPS Clerk26 papersSBI Clerk26 papersRRB Group D26 papersSSC CPO26 papersSSC GD26 papers